How long does it take to produce a double-decker carousel. Usually, the production cycle of double-decker carousel varies mainly depending on its size and the complexity of the double-decker carousel, etc. Especially for customized double merry go round. However, here’s a general overview of the production cycle of the double-decker carousel
Manufacturing and Fabrication of double decker merry go round (8-12 weeks)
The production of double layer carousel mainly contains 4 parts. Frame and structure, carousel figures, mechanical systems, and decorative elements.
Production of frame and structure for double decker carousel
Carousel Figures of double layer carousel
As we all know, the production of double carousel horses is the most time-consuming, and it may take 6-8 weeks to produce 20-30 carousel (animal, carriages, etc.) However, for the production of carousel figures, fiberglass is the most important material. At the same time, it may take 1-3 weeks
Mechanical Systems of the amusement park double decker carousel.
It may takes 4-6 weeks to produce mechanical system of the carousel ride. All in all, included but not limited to the rotating platforms, motors, and electrical systems, etc. What’s more, high quailty and durable.
Decorative Elements for two level carousel ride
Decorative parts like lights, mirrors, paintings, and ornate details are carefully crafted and installed on the carousel. Usually, it may take 2-4 weeks to complete. However, if the decorations are complex(customized images, decals, or special themes, etc), it will require more time in the design and production stages
In short, the production cycle of the double carousel ride is mainly about 8-12 weeks. Besides, customized two level carousel may take 12-13 weeks. So if you are considering to buy a double decker carousel for your carnival business, you should plan ahead. Furthermore, if you are considering to buy a double decker carousel, please feel free to contact Dinis double decker carousel manufacturer.